I did some digging on the FAA site to see if there were any new Universal related cases, and sure enough, there were several for Project 370, the hotel going on the former Wet n Wild park side of the road.
It appears the hotel on that side will consist of two 10-story towers and a four level parking garage. The work schedule aims for a July 2019 completion date.
Below are images of the FAA OE/AAA cases for the towers and parking garage:
West Tower
East Tower
Parking Garage
There were also cases for the cranes that will soon be erected on the site to assemble the towers. I won't bore you by adding three more of the same type of images, so the relevant details are:
Parking Garage Crane Schedule:
02/19/2018 - 04/05/2018
East Tower Crane Schedule:
04/30/2018 - 08/31/2018
West Tower Crane Schedule:
05/07/2018 - 10/12/2018
I didn't see anything for the hotel on the former Wet n Wild parking lot side of the road yet, but I'm sure they'll show up shortly.