The engineers have been on site everyday since it opened. Opening day they only had 3 trains running with one side of the platform open. They have been adding more capacity and have gotten 6 trains with both sides running working pretty well. So they maintained that through peak summer season. Now that summer peak is over it's time to do some more testing and adjusting. That's why we've seen more issues lately. Adding the 7th and 8th trains on has been the toughest so far. Every time the ride sets up, the engineers and programers make notes of the faults on the computer and then work to resolve each issue. Sometimes writing a 100 lines of code per day. They are working hard and they'll get it right. Every first of a kind ride goes through growing pains. Test and adjust. HHN will provide a great opportunity to catch up with all of the issues because the ride will be closed early every day.