I cannot recall, but when a major construction project is underway, do they continue filing for permits for every little thing within that project... a permit for every sink, fountain, toilet, sign, light and concrete pour? I would think the London facades alone would have had thousands of such permits if it is required. I cannot imagine this being the case.
The reason I ask is because this may have no relationship to Potter if it is not behind the major construction walls.
For each project, there will be multiple permits filed. In this case, the main project is demolition, then under that, they filed for a construction wall and pavement/sidewalk.
Right around the time DA started up, Orlando made the permit site tedious to search. But there would be plumbing, electrical, mechanical, and engineering permits under a certain project number, usually starting with a building and/or engineering permit.
The Lost Continent project is 3992.